9.3 4M Change Management
Activity Purpose:

To give visibility of all process/facilities site changes in advance of any change being implemented.

Activity Scope:

The scope of the change notification summary covers all changes made by the tier 1 supplier or their supply chain.



Submission:

The change notification summary sheet shall be submitted every month on or before the 20th of each month regardless of any update.



Phase 1 2 3 4 5
Activity Content  

-Update and submit the 4M change notification for every process change. (See example of "Process / Facility Site Change" sheet for examples of typical process changes)
-Submit documentation on or before 20th of each month.


Output Document -Change Notification Summary
 
 